Development Team members volunteer to own a Sprint Backlog item in Agile
Choose the correct answer from below list
(1)At the Sprint planning meeting.
(2)During the Daily Scrum.
(3)Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though each one may be done by an individual development team member.
(4)Whenever a team member can accommodate more work.
Answer:-(3)Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though each one may be done by an individual development team member. | |