PMO Certified Practitioner Exam (Dumps)
Question No:-31
|
A PMO is in the process of categorizing its functions to identify which ones should be classified as strategic. What is the primary defining characteristic of a strategic PMO function?
1. Contributing to the organization's strategic planning and goal setting
2. Being executed exclusively by members of upper management
3. Being directly related to organizational strategy or upper management objectives
4. Being directly connected to the organization's core business processes
Answer:-1. Contributing to the organization's strategic planning and goal setting
Note:-Strategic PMO functions are characterized by their direct contribution to organizational strategy, including activities such as portfolio management, aligning initiatives with long-term goals, and advising on resource prioritization. These functions emphasize planning and alignment at the highest organizational levels.
|
|
Question No:-32
|
A company is evaluating its PMO to understand its contribution to organizational success. Some team members suggest that a mature organization naturally leads to a mature PMO, while others argue that they are separate concepts that need to evolve together. How should the relationship between organizational project management maturity and PMO maturity be understood?
1. The existence of a PMO itself indicates a certain level of organizational maturity, showing that the organization is ready to implement formal project management practices
2. All of the above, as each perspective offers a different but valid understanding of how organizational maturity and PMO maturity are connected
3. Organizational maturity and PMO maturity are distinct yet interrelated, evolving independently while complementing and, at times, limiting each other to drive project management success
4. Organizational maturity is essential for the establishment of a PMO, as only a mature organization can effectively support a structured and impactful PMO
Answer:-3. Organizational maturity and PMO maturity are distinct yet interrelated, evolving independently while complementing and, at times, limiting each other to drive project management success
Note:-Organizational maturity and PMO maturity are interrelated but distinct concepts. Both must evolve independently while complementing each other to achieve project success. For instance, a mature PMO can drive organizational improvement, while an organization with high maturity supports effective PMO operations.
|
|
Question No:-33
|
A newly appointed PMO professional has been tasked with developing an organizational project management (OPM) competency framework to improve project management across the organization. The goal is to ensure alignment with both industry standards and specific organizational needs.
What should the PMO professional do first?
1. Create a list of competencies based on the organization's past project successes.
2. Analyze the project management skills of the current team and develop a framework around their existing competencies.
3. Research industry standards and good practices, then adapt them to address the organization's unique challenges.
4. Focus the competency framework on senior project managers, as they will have the most impact on the organization's success.
Answer:-3. Research industry standards and good practices, then adapt them to address the organization's unique challenges.
|
|
Question No:-34
|
The executive team is concerned with the performance of a PMO. Some customers have complained that service delivery is inconsistent.
What should the PMO professional do first to address these concerns?
1. Present the PMO's benefits realized to the executive team and customers.
2. Meet with customers and check if a reassessment of expectations is needed.
3. Increase the number of PMO services offered to its customers.
4. Review the service quality metrics for customers regularly to drive consistency.
Answer:-4. Review the service quality metrics for customers regularly to drive consistency.
|
|
Question No:-35
|
A company has a history of struggling to deliver projects on time and within budget. The PMO professional has been tasked with assessing the maturity and capability of the PMO in order to develop a plan for improvement.
What should the PMO professional do?
1. Hire a consultant to conduct a PMO maturity assessment.
2. Interview PMO team members and stakeholders and record their suggestions.
3. Review the PMO documentation for information on PMO maturity models.
4. Conduct a self-assessment using a PMO maturity model.
Answer:-4. Conduct a self-assessment using a PMO maturity model.
|
|
|