To improves our performance please Like Share Subscribe(Will boost us)
|
|
|
| In a team, if someone gets stuck with the selected tasks for the iteration, what is the immediate next step? Question Posted on 02 Apr 2023 Home >> Agile >> Agile Practitioners >> In a team, if someone gets stuck with the selected tasks for the iteration, what is the immediate next step? |
| In a team, if someone gets stuck with the selected tasks for the iteration, what is the immediate next step?
Choose the correct option from below list
(1)Without wasting time, the team member has to inform the Lead/Onsite coordinator and take up another task.
(2)The team member should reach out to other team members tor help.
(3)The team member should wait tor the Team Retrospective to discuss the issue.
(4)Team member must inform the Product Owner and pick up another task.
Answer:-(2)The team member should reach out to other team members tor help. | | |
|